Physical Security Professional Certification Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the Physical Security Professional Certification Exam with flashcards and multiple choice questions. Each question provides hints and detailed explanations. Master your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What is NOT a phase in the implementation of physical protection systems?

  1. Execution

  2. Development

  3. Feasibility

  4. Close out

The correct answer is: Development

The correct answer is "Development." In the context of implementing physical protection systems, the phases typically include the feasibility assessment, execution of the system, and the close-out phase, which involves evaluating the project's success and ensuring that all objectives were met. The feasibility phase is essential as it determines if the proposed protection system can effectively meet security needs within the given constraints. Execution refers to the actual implementation of the physical protection measures, where components are put in place, and operational protocols are established. The close-out phase involves a thorough review of the system’s performance, addressing any outstanding issues, and formally concluding the project. In contrast, the term "Development" is not typically recognized as a distinct phase in the implementation process. While development might take place during the planning and design stages, it is not categorically defined as a standalone phase in the context of implementing physical protection systems. Understanding these phases is crucial for effective security planning and management.